Heavy & Civil Construction contracts at Naval Base Kitsap Bangor
Numbers cover FY2021–FY2025 (Oct 2020 – Sep 2025). Data as of Oct 21, 2026; complete through Jul 13, 2026. Data status
Open Heavy & Civil Construction bids here now
No open Heavy & Civil Construction bids here right now. Updated weekly from SAM.gov · data through Oct 25. Save this search
Typical award (median)
$3,280,351
The middle of 22 priced awards, FY2021–FY2025. Half were between $640k and $7M.
Typical number of bids
4.5
Median bids per award, reported for 22 of 22 competed awards. 5% drew only one bid.
Won by small businesses
5%
Share of the 22 priced awards.
Median = the middle award: half were smaller, half were larger. Bids = how many offers the agency received.
What this means
- The middle heavy & civil award at Naval Base Kitsap Bangor was $3.3M (FY2021-FY2025, 22 priced awards).
- That is 92% higher than the median for heavy & civil in Washington ($1.7M).
- Competed awards drew a median of 4.5 offers (reported for 22 of 22).
- 5% of competed awards drew only one offer.
- Small businesses won 5% of priced awards.
- Tip 100% of these awards were task orders under multiple-award contracts (MATOCs). To compete for those, you first need a spot on one of the umbrella contracts.
FedComps Pro · coming soon · free waitlist
Get alerts for new heavy & civil work near Naval Base Kitsap Bangor
- Alerts that say if a bid is worth it
- Deadline and amendment alerts
- Recompete radar
- Plain-English bid summaries
- Competitor tracking
- Unlimited saved searches
Planned price: $15/month or $119/year (save 34%), with a 14-day free trial. No card needed to start. Cancel anytime. See pricing
Awards per year
- FY2025, the latest full year: 8 awards
- FY2026 is still being reported
Show the numbers
| Year | Awards | Median award |
|---|---|---|
| FY2016 | 2 | – |
| FY2017 | 1 | – |
| FY2018 | 1 | – |
| FY2019 | 2 | – |
| FY2020 | 4 | – |
| FY2021 | 3 | – |
| FY2022 | 2 | – |
| FY2023 | 5 | $7,289,702 |
| FY2024 | 4 | – |
| FY2025 | 8 | $2,489,000 |
| FY2026 (provisional) | 4 | – |
Award sizes
- Holds the median award, $3,280,351
Recent awards
The latest 25 awards, newest first. Each contract number opens its official record on USAspending.gov.
| Project | How it was awarded | ||||
|---|---|---|---|---|---|
| May 15, 2026 | 57370196 Repair Feeders F611 and F615, Building 7141 Bangor N4425526F0155 on USAspending (opens in a new tab) | Nova Group, Inc. | $794,800 | 1 | Order (multiple-award IDIQ) Open to all |
| Apr 9, 2026 | Replace All Cathodic Protection at B7132, NSWC Car -Bangor N4425526F0053 on USAspending (opens in a new tab) | Manson Construction Co | $745,000 | 3 | Order (multiple-award IDIQ) Open to all |
| Mar 9, 2026 | Repair Conduit, Marginal Pier Fixed Fighting Position, Building 7129 at Naval Base Kitsap, Bangor, Washington N4425526F0088 on USAspending (opens in a new tab) | Nova Group, Inc. | $1,679,500 | 2 | Order (multiple-award IDIQ) Open to all |
| Feb 19, 2026 | Overhaul, Restore, and Repair Marginal Wharf South Shore Power Booms. N4425526F0073 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $887,474 | 3 | Order (multiple-award IDIQ) Open to all |
| Sep 23, 2025 | Remove Marine Growth and Prepare Surfaces of Piles for New Coatings or Wraps. Prime and Paint or Install Protective Wrap Systems to Surfaces of Piles 1-6 and Pile 12: Install New Anodes on the Three Six Total Piles in Pile 6 and 5. N4425525F0272 on USAspending (opens in a new tab) | Nova Group, Inc. | $149,750 | 4 | Order (multiple-award IDIQ) Open to all |
| May 21, 2025 | Design-Bid-Build Project to Repair Small Craft Refueling at Olympic Pier, Bangor N4425525F0063 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $4,777,509 | 6 | Order (multiple-award IDIQ) Open to all |
| May 5, 2025 | Remove and Replace Five 14 Inch Wood Pile and Install Five Anodes to the Five New Steel Pile. Remove and Replace All KB Docks Pier and Trestle Pile Bracing, Cross Bracing and Hardware. N4425525F0025 on USAspending (opens in a new tab) | Manson Construction Co | $662,000 | 5 | Order (multiple-award IDIQ) Open to all |
| Mar 13, 2025 | Waterfront Multi-Award Const. Contract N4425525F4106 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $8,611,602 | 5 | Order (multiple-award IDIQ) Open to all |
| Feb 24, 2025 | Align Rails on Naval Base Kitsap, Silverdale, Washington N4425525F4077 on USAspending (opens in a new tab) | Nova Group, Inc. | $781,000 | 3 | Order (multiple-award IDIQ) Open to all |
| Dec 13, 2024 | Repair Support Systems, Marginal, B-7176 N4425525F4007 on USAspending (opens in a new tab) | Nova Group, Inc. | $4,197,000 | 3 | Order (multiple-award IDIQ) Open to all |
| Dec 12, 2024 | Replace Fuel Line N4425525F4028 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $386,625 | 1 | Order (multiple-award IDIQ) Open to all |
| Dec 11, 2024 | N4425521D5008 / N4425525F4009 RM21-0787 Explosive Handling Wharf 1 (EHW1) Electrical Refurbishment, Bangor, Silverdale, WA N4425525F4009 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $13,788,400 | 4 | Order (multiple-award IDIQ) Open to all |
| Sep 4, 2024 | Repair Existing Delta South Inboard FWD Shore Power Transformer, Delta Pier, Naval Base Kitsap, Bangor, Washington N4425524F4341 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $632,500 | 4 | Order (multiple-award IDIQ) Open to all |
| Apr 25, 2024 | The Project Is High Priority Emergency Repair Work Required Road, IT Includes Structural Repairs to the Roadway Providing for Concrete Paving Elements Along with the Reset of Manholes, Precast Culverts, Sheet Piles... N4425524F4178 on USAspending (opens in a new tab) | Contrack Watts Inc | $21,274,800 | 3 | Order (multiple-award IDIQ) Open to all |
| Apr 2, 2024 | Construct BROW Landing Platforms for Blocking Vessels, Bangor, Washington. N4425524F4144 on USAspending (opens in a new tab) | Nova Group, Inc. | $89,500 | 2 | Order (multiple-award IDIQ) Open to all |
| Dec 20, 2023 | Finger Piers N0016724P0029 on USAspending (opens in a new tab) Equipment purchase | Chinook Properties, Inc. | $617,000 | 3 | Competed Small business |
| Dec 20, 2023 | Design Build Marginal Wharf Shore Power Relays, Building 7176, Naval Base Kitsap, Bangor, Washington N4425524F4043 on USAspending (opens in a new tab) | Nova Group, Inc. | $1,420,000 | 5 | Order (multiple-award IDIQ) Open to all |
| Aug 29, 2023 | P907 Transit Protection System (TPS) Fueling and Vessel, Bangor, Silverdale, WA N4425523F4445 on USAspending (opens in a new tab) | Contrack Watts Inc | $29,045,500 | 4 | Order (multiple-award IDIQ) Open to all |
| Jun 9, 2023 | Replace Sod Vent Piping, Building 7137, Naval Base Kitsap, Bangor N4425523F4319 on USAspending (opens in a new tab) | Nova Group, Inc. | $920,500 | 2 | Order (multiple-award IDIQ) Open to all |
| Apr 5, 2023 | Seismic Repairs, TRF, Naval Submarine Base Bangor, Silverdale, WA N4425523F4260 on USAspending (opens in a new tab) Cancelled / $0 | Kiewit-Alberici Siop Macc Ajv | $75,000,000 | 1 | Order (multiple-award IDIQ) Open to all |
| Mar 28, 2023 | X004 Replace Delta Pier Switching Station, B7035, Bangor N4425523F4222 on USAspending (opens in a new tab) | Nova Group, Inc. | $9,450,000 | 4 | Order (multiple-award IDIQ) Open to all |
| Mar 1, 2023 | Replace Critical Structure Piles, EHW-1, 7501, Bangor N4425523F4213 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $7,289,702 | 6 | Order (multiple-award IDIQ) Open to all |
| Dec 9, 2022 | P454 Multi-Mission Dry Dock - Early Contractor Involvement N4425523F4030 on USAspending (opens in a new tab) | TPC-Nan A Joint Venture | $75,000 | 5 | Order (multiple-award IDIQ) Open to all |
| Sep 8, 2022 | Fabricate Install Two New Mooring Camels, Bangor, Silverdale, WA N4425522F4363 on USAspending (opens in a new tab) | Manson Construction Co | $6,319,000 | 6 | Order (multiple-award IDIQ) Open to all |
| Jun 10, 2022 | RM 15-1525 Replace Mooring Rails EHW-1, Bangor, WA N4425522F4214 on USAspending (opens in a new tab) | Triton Marine Construction Corp. | $3,097,702 | 6 | Order (multiple-award IDIQ) Open to all |
Value at award = the contract value when it was signed. Bids = offers received; "–" means not reported. Set-aside = reserved for a group, such as small or veteran-owned businesses. IDIQ = an umbrella contract; work under it is placed as task orders.
Who won
Companies with the most priced awards here, FY2021–FY2025.
| # | Company | Awards | Total value at award |
|---|---|---|---|
| 1 | Triton Marine Construction Corp. | 7 | $38,584,040 |
| 2 | Nova Group, Inc. | 7 | $17,007,750 |
| 3 | Contrack Watts Inc | 4 | $59,839,300 |
| 4 | Manson Construction Co | 2 | $6,981,000 |
| 5 | TPC-Nan A Joint Venture | 1 | $75,000 |
| 6 | R.E. Staite Engineering, Inc. | 1 | $5,000 |
How the work was bought
Competition
Was the work open to bids?
- Order (multiple-award IDIQ) 22 (100%)
A task order placed under an IDIQ held by several companies, who competed for it.
Set-asides
Set-aside = reserved for a group of businesses.
- Open to all 22 (100%)
No set-aside: any size of business could bid.
Left out of the numbers above: 1 equipment purchase, 7 cancelled or $0 awards. Why?
Contracting offices buying here
Umbrella contracts used here
Many jobs are placed as task orders under an IDIQ: an umbrella contract with no fixed amount. Only the companies holding it can get those orders. A "multiple-award" IDIQ is shared by several companies, who compete for each order. "–" = not reported.
| Contract | Type | Orders | Ordering ends |
|---|---|---|---|
| N4425521D5005 | Multiple-award The IDIQ drew 9 offers | 7 | Feb 25, 2027 |
| N4425521D5008 | Multiple-award The IDIQ drew 9 offers | 7 | Feb 25, 2027 |
| N4425521D5003 | Multiple-award The IDIQ drew 9 offers | 4 | Feb 25, 2027 |
| N4425521D5004 | Multiple-award The IDIQ drew 9 offers | 2 | Feb 25, 2027 |
| N4425521D5006 | Multiple-award The IDIQ drew 9 offers | 1 | Feb 25, 2027 |
Other trades here
Report an error on this page