Typical award (median)
$80,676
The middle of 40 priced awards, FY2021–FY2025. Half were between $45k and $228k.
Typical number of bids
2.5
Median bids per award, reported for 10 of 10 competed awards. 10% drew only one bid.
Won by small businesses
100%
Share of the 40 priced awards.
Median = the middle award: half were smaller, half were larger. Bids = how many offers the agency received.
What this means
- The middle building construction award from SER East MABO was $80.7k (FY2021-FY2025, 40 priced awards).
- That is 55% lower than the median for building construction nationwide ($178k).
- Competed awards drew a median of 2.5 offers (reported for 10 of 10).
- 10% of competed awards drew only one offer.
- Small businesses won 100% of priced awards.
- Tip 100% of awards with a reported set-aside were reserved for small businesses, so small firms were not bidding against large companies.
FedComps Pro · coming soon · free waitlist
Get alerts for new building construction work near you
- Alerts that say if a bid is worth it
- Deadline and amendment alerts
- Recompete radar
- Plain-English bid summaries
- Competitor tracking
- Unlimited saved searches
Planned price: $15/month or $119/year (save 34%), with a 14-day free trial. No card needed to start. Cancel anytime. See pricing
Awards per year
- FY2025, the latest full year: 5 awards
- FY2026 is still being reported
Show the numbers
| Year | Awards | Median award |
|---|---|---|
| FY2017 | 2 | – |
| FY2018 | 12 | $121,823 |
| FY2019 | 15 | $73,863 |
| FY2020 | 5 | $47,831 |
| FY2021 | 6 | $60,159 |
| FY2022 | 16 | $80,676 |
| FY2023 | 11 | $76,229 |
| FY2024 | 2 | – |
| FY2025 | 5 | $377,760 |
| FY2026 (provisional) | 3 | – |
Award sizes
- Holds the median award, $80,676
Recent awards
The latest 25 awards, newest first. Each contract number opens its official record on USAspending.gov.
| Project | How it was awarded | ||||
|---|---|---|---|---|---|
| Aug 24, 2026 | Replacement of Video Surveillance System at Various Locations per the Project Specifications and Design Plans for Martin Luther King, Jr. National Historic Park Atlanta, Georgia. 140P5126C0008 on USAspending (opens in a new tab) | Trustedciso LLC | $1,290,000 | 5 | Competed Woman-owned |
| Jun 15, 2026 | EO 14398, Construct a 30'X40' Picnic Pavilion, Andersonville National Historic Site, NPS 140P5126P0040 on USAspending (opens in a new tab) | Jamii Development LLC | $85,200 | 18 | Competed Small business |
| May 18, 2026 | Provide a Historical Preservation Team to Repair the Control Tower Observation Deck and Replace the Fire Escape System for Tuskegee Airmen National Historic Site Tuskegee, Alabama. 140P5126P0034 on USAspending (opens in a new tab) | Dri, Inc. | $138,700 | 5 | Competed Small business |
| Jul 23, 2025 | The Primary Objective of the Project Is to Replace the PONY PEN Hay BARN. The Project Shall Demolish the Old BARN Building Down to Pilings and Girders and Construction of New BARN, Lean Too Shed Roof and Walls to Remain and Be to New Build 140P5125C0021 on USAspending (opens in a new tab) | Individual contractor (name withheld) | $224,303 | 12 | Competed Woman-owned |
| Jul 8, 2025 | Creek Bridge Replacement, Kennesaw Mountain, Kennesaw, Georgia 30152 140P5125C0006 on USAspending (opens in a new tab) | Pci Support Services LLC | $593,253 | 2 | Competed Indian / tribal |
| Jun 11, 2025 | Service, for NPS, Replacement of Gutters at Old Firehouse(VC) at Reconstruction Era National Historic 140P5125P0036 on USAspending (opens in a new tab) Equipment purchase | Collins Construction Services, Inc | $26,022 | 2 | Competed Open to all |
| May 28, 2025 | Replace the Existing Asphalt Sidewalks with New Concrete Sidewalks to Match Concrete Sidewalks That Are Currently in Place Closer to the Visitor Center Building for Kings Mountain National Military Park Blacksburg, South Carolina. 140P5125C0014 on USAspending (opens in a new tab) | Ocs-NCS JV II, LLC | $377,760 | 1 | Not competed 8(a) |
| May 16, 2025 | Contractor Shall Assess the Existing National POW Museum Water Feature and Provide a Written Evaluation Detailing the Needed Improvements to the National POW Museum Water Feature and Implement the Park Staffs Desired Results into Their Evaluation 140P5125C0011 on USAspending (opens in a new tab) | Msab, LLC | $461,699 | 1 | Not competed 8(a) |
| Apr 9, 2025 | Structures with Wood Replacement and Repairs for Tuskegee Airmen National Historic Site. 140P5125C0005 on USAspending (opens in a new tab) | Individual contractor (name withheld) | $14,550 | 2 | Competed Small business |
| Jul 30, 2024 | Replace Old Beaufort Firehouse and Visitor Center Exterior Door and Learning Center Roof Replacement Reconstruction Era National Monument Beaufort, South Carolina. 140P5124C0012 on USAspending (opens in a new tab) | Collins Construction Services, Inc | $105,034 | 1 | Not competed 8(a) |
| Mar 19, 2024 | Construction, Rehabilitation of Prisoner of War Museum Lobby for NPS, Andersonville NHS 140P5124P0015 on USAspending (opens in a new tab) | Msab, LLC | $8,500 | 1 | Competed Small business |
| Feb 16, 2024 | Construction, Rehabilitation of Prisoner of War Museum Lobby for NPS, Andersonville NHS 140P5124C0005 on USAspending (opens in a new tab) Cancelled / $0 | Msab, LLC | $8,500 | 1 | Competed Small business |
| Aug 28, 2023 | Replacement Timber Guardrail at Jones Bridge Unit, Chattahoochee River National Recreation Area 140P5123C0029 on USAspending (opens in a new tab) | Ocs-NCS JV, LLC | $99,633 | 1 | Not competed 8(a) |
| Aug 28, 2023 | Replacement MULE and Enclosures for Jimmy Carter National Historical Park 140P5123C0030 on USAspending (opens in a new tab) | Ajce Corporation | $76,229 | 1 | Not competed 8(a) |
| Jul 27, 2023 | The Removal and Replacement of Approximately 210 Linear Feet of Gutter and Fascia Board and Associated Hardware and Gutter Guard, and the Removal and Replacement of Approximately 120 Linear Feet of Downspout on the Historic Cottage Building at Fort 140P5123C0026 on USAspending (opens in a new tab) | Collins Construction Services, Inc | $9,837 | 3 | Competed Small business |
| Jun 7, 2023 | Removal of the Old Shake Roofing and Underlayment, Inspection for Damage or Deterioration of Any Underlying Decking, Replacement of Decking That Has Deteriorated Because of Leaks or Age, Placement of New Underlayment, and Installation of NE 140P5123C0016 on USAspending (opens in a new tab) | Msab, LLC | $45,663 | 1 | Not competed 8(a) |
| Jun 1, 2023 | Replace Curved Window Units in POW Museum Library and Repair Any Water Damaged Exterior or Interior Surfaces That Have Been Previously Damaged or Damaged in Conjunction with the Removal and Install of the Windows. New Windows Units Shall Provide 140P5123C0018 on USAspending (opens in a new tab) | Msab, LLC | $43,200 | 1 | Not competed 8(a) |
| May 30, 2023 | Clean, Prepare, and Clear Coat Farm. Replace the Wooden Tank Portion of and Reconnect the Tail Boom Spring, Reconnect the Tail Boom Brake Arm, Replace the Fan Brake Chain That Is Currently Broken and from TH 140P5123C0017 on USAspending (opens in a new tab) | Msab, LLC | $62,923 | 1 | Not competed 8(a) |
| May 19, 2023 | Installation of a Dry Pipe Sprinkler System Through the Building, Including the Attic, Porch, and Under Exterior and Roof Gables. Dry Pipe System Shall Utilize a Nitrogen Generator System and Both the N2 System and the Dry Pipe Valve Shall Be 140P5123C0011 on USAspending (opens in a new tab) | Aiko Enterprises, Inc | $798,722 | 2 | Competed Small business |
| May 16, 2023 | The Rehabilitation of the Restrooms and Vestibule Spaces of the Historic Lookout Mountain Visitor's Center. The Rehabilitation Will Focus on the Refresh of Finishes, Select Updates to the Mechanical, Electrical, and Plumbing Systems 140P5123C0008 on USAspending (opens in a new tab) | J. Brennon Construction, Inc. | $604,883 | 1 | Not competed 8(a) |
| Mar 30, 2023 | Replacement of the Cooling Tower and Condenser Water Pumps at Tuskegee Airman National Historic Site, Tuskegee, AL 140P5123C0007 on USAspending (opens in a new tab) | Apex Facility Services Group LLC | $329,520 | 2 | Competed Small business |
| Feb 23, 2023 | Removal of the Existing Incline and Vertical Lifts Within and Installation of a New Incline Lift and New Hybrid Lift. The New Hybrid Lift Requires a Machine Room That Will Be Installed in the Existing Attic 140P5123C0005 on USAspending (opens in a new tab) | Aiko Enterprises, Inc. | $319,835 | 3 | Competed Small business |
| Feb 23, 2023 | Perform Mold Remediation on First Floor Ceiling Hallway, Upper Wall Hallway, Remove Water Stains and Paint Hallway Wall at the Oaks, Home Tuskegee Institute National Historic Site. 140P5123P0015 on USAspending (opens in a new tab) | Provision Contracting Services LLC | $25,413 | 1 | Not competed 8(a) |
| Sep 26, 2022 | Visitor Center Rehabilitation for Russell Cave National Monument, Bridgeport, Alabama 140P5122C0039 on USAspending (opens in a new tab) | Raad Construction Group LLC | $1,257,067 | 4 | Competed Small business |
| Sep 12, 2022 | Improve River Access and New Launch at Power Island Unit Fitness Trail in Chattahoochee River National Recreation Area in Atlanta, GA. 140P5122C0040 on USAspending (opens in a new tab) | National Contracting Services LLC | $564,448 | 1 | Not competed 8(a) |
Value at award = the contract value when it was signed. Bids = offers received; "–" means not reported. Set-aside = reserved for a group, such as small or veteran-owned businesses. IDIQ = an umbrella contract; work under it is placed as task orders.
Who won
Companies with the most priced awards here, FY2021–FY2025.
| # | Company | Awards | Total value at award |
|---|---|---|---|
| 1 | Msab, LLC | 10 | $1,120,588 |
| 2 | National Contracting Services, LLC | 5 | $384,389 |
| 3 | Ajce Corporation | 4 | $327,956 |
| 4 | Collins Construction Services, Inc | 3 | $170,743 |
| 5 | Driven Contractors LLC | 2 | $179,142 |
| 6 | Provision Contracting Services LLC | 2 | $40,157 |
| 7 | Raad Construction Group LLC | 1 | $1,257,067 |
| 8 | Aiko Enterprises, Inc | 1 | $798,722 |
| 9 | J. Brennon Construction, Inc. | 1 | $604,883 |
| 10 | Pci Support Services LLC | 1 | $593,253 |
How the work was bought
Competition
Was the work open to bids?
- Not competed 30 (75%)
Sole-source: only one company was asked.
- Competed 10 (25%)
A standalone contract that was open to bids.
Set-asides
Set-aside = reserved for a group of businesses.
- 8(a) 30 (75%)
Reserved for firms in SBA's 8(a) program for disadvantaged small businesses.
- Small business 8 (20%)
Only small businesses could bid.
- Woman-owned 1 (3%)
Reserved for woman-owned small businesses (WOSB/EDWOSB).
- Indian / tribal 1 (3%)
Reserved for Indian-owned or tribal enterprises (Buy Indian Act, ISBEE).
Left out of the numbers above: 1 equipment purchase, 1 cancelled or $0 award. Why?
Other trades from this office
Report an error on this page
Wrong number, award at the wrong base, or a name that should not be here? Tell us. We check every report and fix the rule behind it.