Typical award (median)
$3,415,248
The middle of 16 priced awards, FY2021–FY2025. Half were between $842k and $9.3M.
Typical number of bids
–
No bid counts: most awards here were orders under single-award contracts, where no one else could bid.
Won by small businesses
0%
Share of the 16 priced awards.
Median = the middle award: half were smaller, half were larger. Bids = how many offers the agency received.
What this means
- The middle construction & facilities award at Radford Army Ammunition Plant was $3.4M (FY2021-FY2025, 16 priced awards).
- That is 65.8 times the median for all construction & facilities work in Virginia ($51.9k).
- Small businesses won 0% of priced awards.
- 100% of priced awards went to companies based within 100 miles of the work.
- 100% of priced awards were task orders under IDIQ contracts.
- Tip 100% of these awards were task orders under single-award contracts (IDIQs). Only the company holding that contract could get them, so watch for the umbrella contract to be re-bid.
FedComps Pro · coming soon · free waitlist
Get alerts for new facilities support work near Radford Army Ammunition Plant
- Alerts that say if a bid is worth it
- Deadline and amendment alerts
- Recompete radar
- Plain-English bid summaries
- Competitor tracking
- Unlimited saved searches
Planned price: $15/month or $119/year (save 34%), with a 14-day free trial. No card needed to start. Cancel anytime. See pricing
Awards per year
- FY2025, the latest full year: no awards
- FY2026 is still being reported
Show the numbers
| Year | Awards | Median award |
|---|---|---|
| FY2016 | 2 | – |
| FY2017 | 3 | – |
| FY2018 | 1 | – |
| FY2019 | 3 | – |
| FY2020 | 6 | $5,179,884 |
| FY2021 | 2 | – |
| FY2022 | 3 | – |
| FY2023 | 8 | $2,182,938 |
| FY2024 | 3 | – |
| FY2025 | 0 | – |
| FY2026 (provisional) | 1 | – |
Award sizes
- Holds the median award, $3,415,248
Recent awards
The latest 25 awards, newest first. Each contract number opens its official record on USAspending.gov.
| Project | How it was awarded | ||||
|---|---|---|---|---|---|
| Jun 29, 2026 | Task Order to Fund Settlement of Request for Equitable Adjustment and Certified Claim Related to 2020-2021 Centerra Labor Rates Related to Services Performed at Radford Army Ammunition Plant W519TC26F0134 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $248,638 | 1 | Order (single-award IDIQ) Open to all |
| Sep 26, 2024 | The Purpose of Task Order W519TC24F0473 Is to Obligate Funds for the PLC Upgrades and Powerhouse Vibration Monitoring Requirement in Support of Radford Army Ammunition Plant. W519TC24F0473 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $288,009 | 1 | Order (single-award IDIQ) Open to all |
| Jun 24, 2024 | Incorporate a Requirement to Perform Phase 2 of the Effort to Stabilize the Legacy NG-2 Area Facility Including the Energetic Waste Incinerator at the Radford Army Ammunition Plant W519TC24F0063 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $4,178,433 | 1 | Order (single-award IDIQ) Open to all |
| Oct 25, 2023 | Completion of Phase I to the Overall Legacy Facility Replacement Effort to Produce a 15% Design, Including an Option for Completion to 30% Design for a New Multi Manufacturing Facility at Radford Army Ammunition Plant. W519TC24F0011 on USAspending (opens in a new tab) Unusually large Approx. location | Bae Systems Ordnance Systems Inc | $23,551,294 | 1 | Order (single-award IDIQ) Open to all |
| Sep 29, 2023 | The Purpose of to W519TC23F0548 Is to Incorporate Phase 2 of the Requirement to Stabilize and Repair Rocket Area at Radford Army Ammunition Plant W519TC23F0548 on USAspending (opens in a new tab) Unusually large Approx. location | Bae Systems Ordnance Systems Inc | $12,316,284 | 1 | Order (single-award IDIQ) Open to all |
| Sep 26, 2023 | This Task Order Is to Fund the Fourth and Final Phase of Arc Flash Hazard Assessment at the Radford Army Ammunition Plant. W519TC23F0522 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $939,284 | 1 | Order (single-award IDIQ) Open to all |
| Sep 18, 2023 | The Purpose of to W519TC23F0443 Is to Incorporate a Requirement for Compressed Air House Control System Improvements at the Radford Army Ammunition Plant W519TC23F0443 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $2,652,062 | 1 | Order (single-award IDIQ) Open to all |
| Sep 1, 2023 | Undefinitized Contract Action for Advanced Ammunition Phase II at Radford Army Ammunition Plant W519TC23F0408 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $1,713,814 | 1 | Order (single-award IDIQ) Open to all |
| Aug 18, 2023 | Upgrade to Rocket Propellant Manufacturing at Radford Army Ammunition Plant. Upgrades Include Area and CNC Area to Produce the MK90 Grain and Other Caliber Grains in a More Efficient and Safe Environment. W519TC23F0341 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $6,761,808 | 1 | Order (single-award IDIQ) Open to all |
| Jun 15, 2023 | Maintenance Work to the Building 1814 Barricade at the Radford Army Ammunition Plant. W519TC23F0255 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $176,321 | 2 | Order (single-award IDIQ) Open to all |
| May 18, 2023 | Task Order W519TC-23-F-0202 Under Basic Ordering Agreement W52P1J-11-G-0002 Incorporates a Requirement for Life Cycle Pilot Process - Alternative Blending Technologies Phase 2 at the Radford Army Ammunition Plant. W519TC23F0202 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $549,445 | 1 | Order (single-award IDIQ) Open to all |
| Nov 30, 2022 | Task Order W519TC23F0017 Is Issued for Award of an UCA for Construction of a New Chemical Grind Facility at Radford Army Ammunition Plant. W519TC23F0017 on USAspending (opens in a new tab) Unusually large Approx. location | Bae Systems Ordnance Systems Inc | $39,477,134 | 1 | Order (single-award IDIQ) Open to all |
| Sep 29, 2022 | Task Order Under Basic Ordering Agreement W52P1J-11-G-0002 Incorporates a Requirement for NAC/Sac Process Improvements at the Radford Army Ammunition Plant. W52P1J22F0124 on USAspending (opens in a new tab) Unusually large Approx. location | Bae Systems Ordnance Systems Inc | $11,721,082 | 1 | Order (single-award IDIQ) Open to all |
| Sep 13, 2022 | Task Order W52P1J22F0422 Under BOA W52P1J11G0002 Supports the Arms Metal Parts Effort at the Radford Army Ammunition Plant. W52P1J22F0422 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $1,633,159 | 1 | Order (single-award IDIQ) Open to all |
| Dec 9, 2021 | Upgrade/Replace 2", 2.5", and 4 Fire Protection Systems in Various Buildings at Radford Army Ammunition Plant, As Set Forth in Attachment 0001, Statement of Work (SOW) Fire Protection System (Deluge Valves) Upgrade. W52P1J22F0022 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $8,504,429 | 1 | Order (single-award IDIQ) Open to all |
| Sep 24, 2021 | Task Order W52P1J-21-F-0552 Under W52P1J-11-G-0002 Supports FY21 Army Materiel Command Builder Support Assessment at Radford Army Ammunition Plant. W52P1J21F0552 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $144,225 | 1 | Order (single-award IDIQ) Open to all |
| Jun 10, 2021 | Task Order W52P1J21F0003 Under W52P1J-11-G-0002 Supports the NC Slurry Transfer Line Project at Radford Army Ammunition Plant W52P1J21F0030 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $4,474,546 | 1 | Order (single-award IDIQ) Open to all |
| Sep 25, 2020 | Arc Flash Hazard Assessment Phase III at Radford Army Ammunition Plant W52P1J20F0661 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $589,757 | 1 | Order (single-award IDIQ) Open to all |
| Sep 3, 2020 | The Purpose of Task Order W52P1J -20-F-0614 Under Basic Ordering Agreement W52P1J-11-G-0002 Is to Upgrade, Replace or Demolish 12 Different Barricades at Radford Army Ammunition Plant. W52P1J20F0614 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $9,641,028 | 1 | Order (single-award IDIQ) Open to all |
| Sep 1, 2020 | Task Order W52P1J20F0405 Under W52P1J-11-G-0002 Supports the Solvent Propellant Facility Sustainment, Phase I, Effort at the Radford Army Ammunition Plant. W52P1J20F0405 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $5,900,474 | 1 | Order (single-award IDIQ) Open to all |
| Apr 29, 2020 | The Purpose of Task Order W52P1J20F0314 Under Basic Ordering Agreement W52P1J-11-G-0002 Is to Incorporate a Requirement for Cybersecurity Resiliency at Radford Army Ammunition Plant. W52P1J20F0314 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $704,082 | 1 | Order (single-award IDIQ) Open to all |
| Dec 13, 2019 | The Purpose of Task Order W52P1J-20-F-0096 Under W52P1J-11-G-0002 Is to Incorporate a Requirement to Stabilize and Repair Rocket Area at Radford Army Ammunition Plant. W52P1J20F0096 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $4,459,295 | 1 | Order (single-award IDIQ) Open to all |
| Oct 11, 2019 | The Purpose of Task Order W52P1J-20-F-0021 Under W52P1J-11-G-0002 Is to Incorporate a Requirement to Stabilize the Legacy NG-2 Area Facility at Radford Army Ammunition Plant, As Set Forth in Attachment 0001, NG2 Area Sustainment - Statement of Work. W52P1J20F0021 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $8,309,050 | 1 | Order (single-award IDIQ) Open to all |
| Sep 27, 2019 | Task Order W52P1J-19-F-0797 Under W52P1J-11-G-0002 Incorporates a Government Requirement for Structural Repairs (Phase I) at Radford Army Ammunition Plant W52P1J19F0797 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $1,340,718 | 1 | Order (single-award IDIQ) Open to all |
| Sep 9, 2019 | The Purpose of Task Order W52P1J-19-F-0522 Under W52P1J-11-G-0002 Is to Incorporate a Requirement to the Facility Change House and Restroom Upgrades at Radford Army Ammunition Plant. W52P1J19F0522 on USAspending (opens in a new tab) Approx. location | Bae Systems Ordnance Systems Inc | $5,013,984 | 1 | Order (single-award IDIQ) Open to all |
Value at award = the contract value when it was signed. Bids = offers received; "–" means not reported. Set-aside = reserved for a group, such as small or veteran-owned businesses. IDIQ = an umbrella contract; work under it is placed as task orders.
Who won
Companies with the most priced awards here, FY2021–FY2025.
| # | Company | Awards | Total value at award |
|---|---|---|---|
| 1 | Bae Systems Ordnance Systems Inc | 16 | $119,081,327 |
How the work was bought
Competition
Was the work open to bids?
- Order (single-award IDIQ) 16 (100%)
A task order under an IDIQ held by one company. No new competition, so it is left out of bid statistics.
Set-asides
Set-aside = reserved for a group of businesses.
- Open to all 16 (100%)
No set-aside: any size of business could bid.
Contracting offices buying here
Umbrella contracts used here
Many jobs are placed as task orders under an IDIQ: an umbrella contract with no fixed amount. Only the companies holding it can get those orders. A "multiple-award" IDIQ is shared by several companies, who compete for each order. "–" = not reported.
| Contract | Type | Orders | Ordering ends |
|---|---|---|---|
| W52P1J11G0002 | Single-award | 16 | Dec 31, 2026 |
Other bases & VA centers
- Fort Belvoir
- Naval Station Norfolk
- Joint Base Langley-Eustis
- Naval Air Station Oceana
- Marine Corps Base Quantico
- Naval Support Facility Dahlgren
- Naval Support Activity Norfolk NSY
- Joint Expeditionary Base Little Creek-Fort Story
- Pentagon
- Naval Medical Center Portsmouth
- Defense Supply Center Richmond
- Naval Weapons Station Yorktown
Show all 26
- Fort Lee
- Coast Guard Training Center Yorktown
- VA Richmond
- Joint Base Myer-Henderson Hall
- VA Hampton
- VA Salem
- Naval Support Activity Hampton Roads
- Mark Center
- Fort A.P. Hill
- Coast Guard Base Portsmouth
- Joint Expeditionary Base Little Creek-Fort Story - Wallops Island
- Craney Island
- Fort Pickett
- Arlington National Cemetery
Report an error on this page
Wrong number, award at the wrong base, or a name that should not be here? Tell us. We check every report and fix the rule behind it.